7-year project roadmap · 2026 → 2032

Project plan in 6 phases

From initiation to BYT Care steady-state. Click any phase to see its goal, ownership and outputs.

Project goal
Development + BYT Care
≥ 15% profit margin
Total outputs
94
6 phases
Active outputs
44
Phase I + II
Team
11
+ 17 external partners
Deliverables

Outputs by phase

Every deliverable across the 6 phases. Click any to see what gets measurably delivered and who is responsible.

Project timeline

When work happens

Each output mapped across the 16-month Phase I + Phase II schedule. Solid cells are core work, lighter cells are prep or continuation.

Output
2026
2027
Q1
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Faza I Inicijacija projekta (predpripremna faza)
Faza II Planiranje, dokumentacija i pre-sales
Primary work
Prep / continuation
· Owner colors applied per row for quick scanning
Team & accountability

Who runs what

Click any person or partner to see all outputs they own, lead, are consulted on, or kept informed about.

Leadership (5)
Internal team (6)
External partners
Architects & Design · 6
Legal & Finance · 3
Engineering · 5
Operations & Consulting · 3